Consider the following activities in a building construction?
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
A. 1,3,2,4
B. 3,1,4,2
C. 3,1,2,4
D. 1,3,4, 2
Related Mcqs:
- Select the incorrect statement?
- A. Earliest start of an activity is the early event time of the node it leaves. B. Latest finish of an activity is the late event time of the node it enters. C. Latest start of an activity is its latest finish minus its duration. D. none of the above...
- If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is_________________?
- A. 500 cum B. 1000 cum C. 1500 cum D. 2000 cum...
- Wheeled tractors are replacing crawler tractors because________________?
- Consider the following statements? 1. wheeled tractors travel faster 2. crawler tractors are more expensive 3. track parts of a crawler wear out quickly 4. crawler tractors have stick control A. 1,3 and 4 are correct B. 2, 3 and 4 are correct C. 1,2 and 3 are correct D. 1, 2 and 4 are … Wheeled tractors are replacing crawler tractors because________________?Read More...
- A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be________________?
- A. Rs.1740 B. Rs.3480 C. Rs.5220 D. Rs.6960...
- Slack time refers to_______________?
- A. an activity B. an event C. both event and activity D. none of the above...
Recent Comments