.Management Sciences
A. most likely time
B. optimistic time
C. pessimistic time
D. expected time
Related Mcqs:
- If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then______________?
- A. expected time of activity A is greater than the expected time of activity B B. expected time of activity B is greater than the expected time of activity A C. expected time of both activities A and B are same D. none of the above...
- Consider the following statements for a power shovel?
- (i) Output can be increased by reducing the angle of swing for a given depth of cut (ii) For a given angle of swing, output will be maximum at optimum depth of cut (iii) Output can be increased by keeping the depth of cut less than optimum depth (iv) Output can be increased by increasing … Consider the following statements for a power shovel?Read More...
- Sinking fund is_______________?
- A. the fund for rebuilding a structure when its economic life is over B. raised to meet maintenance costs C. the total sum to be paid to the municipal authorities by the tenants D. a part of the money kept in reserve for providing additional structures and structural modifications...
- A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be________________?
- A. Rs.1740 B. Rs.3480 C. Rs.5220 D. Rs.6960...
- The constraints in case of resource smoothening operation would be_______________?
- A. resources B. project duration time C. both resources and project duration time D. none of the above...