Search
.Management Sciences
A. A critical path always begins at the very first event
B. A critical path always terminates at the last event
C. Critical activities control the project duration
D. Critical activity is the one for which free float is zero
Related Mcqs:
- Critical path_____________?
- A. is always longest B. is always shortest C. may be longest D. may be shortest...
- A machine is purchased for Rs. 10,000,00/- and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000/-. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is__________________?
- A. Rs. 4,75,000/- B. Rs. 5,75,000/- C. Rs. 6,50,000/- D. Rs. 8,50,000/-...
- In resources levelling________________?
- A. total duration of project is reduced B. total duration of project is increased C. uniform demand of resources is achieved D. cost of project is controlled...
- If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be__________________?
- A. 2.3% and 84.1% B. 97.7% and 84.1% C. 97.7 % and 15.9% D. 15.9% and 97.7%...
- Crash project duration is obtained by summing the________________?
- A. normal durations for all the activities B. crash durations for all activities C. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities D. crash durations for all the activities along the critical path obtained by taking into account the crash duration … Crash project duration is obtained by summing the________________?Read More...
Recent Comments