.Management Sciences
A. on commencement of work at site for payment of loan taken by him
B. for the purchase of construction materials
C. for the payment of advances to labour and other staff
D. for all activities required to start the work at site on finalization of the contract document
Related Mcqs:
- The normal time required for the completion of project in the above problem is_______________?
- A. 9 days B. 13 days C. 14 days D. 19 days...
- Sinking fund is_______________?
- A. the fund for rebuilding a structure when its economic life is over B. raised to meet maintenance costs C. the total sum to be paid to the municipal authorities by the tenants D. a part of the money kept in reserve for providing additional structures and structural modifications...
- The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be________________?
- A. Rs. 8,800/- B. Rs. 7,600/- C. Rs. 6,400/- D. Rs. 5,000/-...
- Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing Reason R: If the angle of swing is decreased, the cycle time will be decreased_______________?
- A. Both A and R are true and R is the correct explanation of A B. Both A and R are true but R is not the correct explanation of A C. A is true but R is false D. A is false but R is true...
- Free float is mainly used to_________________?
- A. identify the activities which can be delayed without affecting the total float of preceding activity B. identify the activities, which can be delayed without affecting the total float of succeeding activity C. establish priorities D. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities...