A. greater than or equal to latest event time of preceding node
B. less than or equal to latest event time of preceding node
C. equal to latest event time of preceding node
D. less than latest event time of preceding node
Related Mcqs:
- The reduction in project time normally results in_______________?
- A. decreasing the direct cost and increasing indirect cost B. increasing the direct cost and decreasing the indirect cost C. increasing the direct cost and indirect cost both D. decreasing the direct cost and indirect cost both...
- Rolling resistance of a wheel depends upon_____________?
- (i) Vehicle load (ii) Grade (iii) Ground select the correct statements? A. only (i) is correct B. (i) and (ii) are correct C. (i) and (iii) are correct D. (ii) and (iii) are correct...
- The most suitable type of equipment for compaction of cohesive soils is_________________?
- A. Smooth-wheeled rollers B. Vibratory rollers C. Sheep foot rollers D. Tampers...
- A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be________________?
- A. Rs.1740 B. Rs.3480 C. Rs.5220 D. Rs.6960...
- If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?
- A. 3.5 and 5/6 B. 5 and 25/36 C. 3.5 and 25/36 D. 4 and 5/6...