Consider the following statements ?
1. greater than Total Float.
2. greater than Independent Float
3. equal to Total Float.
4. less than Independent Float. Of these statements
A. 1 and 4 are correct
B. 2 and 3 are correct
C. 1 and 4 are correct
D. 1 and 2 are correct
Related Mcqs:
- Whenever an activity has zero total float, then_______________?
- A. free float of the activity must be zero but independent float need not be zero B. independent float must be zero but free float need not be zero C. free float and independent float both must be zero D. free float and independent float both need not be zero...
- If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is_________________?
- A. 500 cum B. 1000 cum C. 1500 cum D. 2000 cum...
- The correct sequence of these operations in tunnel construction is______________?
- Consider the following operations : 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete A. 1,2,4,3,5 B. 1,3,2,4,5 C. 1,2,3,4,5 D. 1,3,4,2,5...
- The correct sequence of these activities is________________?
- Consider the following activities in a building construction? 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace A. 1,3,2,4 B. 3,1,4,2 C. 3,1,2,4 D. 1,3,4, 2...
- What estimate would you give for the variance in above problem ?
- A. 81 B. 54 C. 36 D. 9...
Recent Comments