A. equal to X
B. more than X
C. less than X
D. any of the above
Related Mcqs:
- The normal time required for the completion of project in the above problem is_______________?
- A. 9 days B. 13 days C. 14 days D. 19 days...
- Sinking fund is_______________?
- A. the fund for rebuilding a structure when its economic life is over B. raised to meet maintenance costs C. the total sum to be paid to the municipal authorities by the tenants D. a part of the money kept in reserve for providing additional structures and structural modifications...
- The correct sequence of these activities is________________?
- Consider the following activities in a building construction? 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace A. 1,3,2,4 B. 3,1,4,2 C. 3,1,2,4 D. 1,3,4, 2...
- Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
- A. Ice B. Concrete C. Loose sand D. Earth...
- The time with which direct cost does not reduce with the increase in time is known as_________________?
- A. crash time B. normal time C. optimistic time D. standard time...