A. 4 days
B. 6 days
C. 10 days
D. 16 days
Related Mcqs:
- The reduction in project time normally results in_______________?
- A. decreasing the direct cost and increasing indirect cost B. increasing the direct cost and decreasing the indirect cost C. increasing the direct cost and indirect cost both D. decreasing the direct cost and indirect cost both...
- If the gross vehicle weight of a truck is 30 t and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is__________________?
- A. 30 kg B. 300 kg C. 900 kg D. 1000 kg...
- The correct sequence of these activities is________________?
- Consider the following activities in a building construction? 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace A. 1,3,2,4 B. 3,1,4,2 C. 3,1,2,4 D. 1,3,4, 2...
- Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
- A. Concrete B. Loose sand C. Asphalt D. Firm earth...
- Select the correct statement?
- A. Activity arrows in a CPM network are drawn to scale B. The tail of an arrow represents the finish of an activity C. Arrow bead represents the start of an activity D. none of the above...