A. identify the activities which can be delayed without affecting the total float of preceding activity
B. identify the activities, which can be delayed without affecting the total float of succeeding activity
C. establish priorities
D. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Related Mcqs:
- Select the incorrect statement?
- A. Earliest start of an activity is the early event time of the node it leaves. B. Latest finish of an activity is the late event time of the node it enters. C. Latest start of an activity is its latest finish minus its duration. D. none of the above...
- Rolling resistance of a wheel depends upon_____________?
- (i) Vehicle load (ii) Grade (iii) Ground select the correct statements? A. only (i) is correct B. (i) and (ii) are correct C. (i) and (iii) are correct D. (ii) and (iii) are correct...
- Sensitivity analysis is a study of__________________?
- A. comparison of profit and loss B. comparison of assets and liabilities C. change in output due to change in input D. economics of cost and benefits of the project...
- If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________________?
- A. 50% B. less than 50% C. more than 50% D. 100%...
- Economic saving of time results by crashing_________________?
- A. cheapest critical activity B. cheapest non-critical activity C. costliest critical activity D. costliest non-critical activity...
Recent Comments