.Management Sciences
A. 8 days
B. 9 days
C. 10 days
D. 15 days
Related Mcqs:
- Which of the following does not represent an activity?
- A. site located B. foundation is being dug C. the office area is being cleaned D. the invitations are being sent...
- A machine is purchased for Rs. 10,000,00/- and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000/-. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is__________________?
- A. Rs. 4,75,000/- B. Rs. 5,75,000/- C. Rs. 6,50,000/- D. Rs. 8,50,000/-...
- In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?
- A. longest duration B. highest cost slope C. least cost slope D. shortest duration...
- If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________________?
- A. 50% B. less than 50% C. more than 50% D. 100%...
- Slack time refers to_______________?
- A. an activity B. an event C. both event and activity D. none of the above...