A. Rs. 8,43,750/-
B. Rs. 8,75,000/-
C. Rs. 10,50,000/-
D. Rs. 11,56,250/-
Related Mcqs:
- Which of the following excavators is most suitable for digging under water?
- A. Drag line B. Hoe C. Clam shell D. Dipper shovel...
- For excavating utility trenches with precise control of depth, the excavation equipment used is_______________?
- A. Hoe B. Shovel C. Dragline D. None of the above...
- Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
- A. on commencement of work at site for payment of loan taken by him B. for the purchase of construction materials C. for the payment of advances to labour and other staff D. for all activities required to start the work at site on finalization of the contract document...
- Crash project duration is obtained by summing the________________?
- A. normal durations for all the activities B. crash durations for all activities C. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities D. crash durations for all the activities along the critical path obtained by taking into account the crash duration … Crash project duration is obtained by summing the________________?Read More...
- In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?
- A. normal distribution curve B. Poisson’s distribution curve C. Beta – distribution curve D. none of the above...