.Management Sciences
A. BCWS
B. EVA
C. BAC
D. CBSE
Explanation: The earned value system provides a common value scale for every task, regardless of the type of work being performed. The total hours to do the whole project are estimated, and every task is given an earned value based on its estimated percentage of the total.
advertisement
Related Mcqs:
- Which of the following is/are main parameters that you should use when computing the costs of a software development project ?
- A. travel and training costs B. hardware and software costs C. effort costs (the costs of paying software engineers and managers) D. all of the mentioned...
- Which of the following costs is not part of the total effort cost ?
- A. Costs of networking and communications B. Costs of providing heating and lighting office space C. Costs of lunch time food D. Costs of support staff...
- Which one is not a risk management activity ?
- A. Risk assessment B. Risk generation C. Risk control D. None of the mentioned...
- Which of the following is a people-intensive activity ?
- A. Problem solving B. Organization C. Motivation D. Project management...
- Which of the following term is best defined by the statement “The creation of a new codeline from a version in an existing codeline” ?
- A. Branching B. Merging C. Codeline D. Mainline...
Recent Comments