.Management Sciences
A. EV = (Sopt + 4Sm + Spess)/4
B. EV = (Sopt + 4Sm + Spess)/6
C. EV = (Sopt + 2Sm + Spess)/6
D. EV = (Sopt + 2Sm + Spess)/4
Explanation: This assumes that there is a very small probability that the actual size result will fall outside the optimistic or pessimistic values.
Related Mcqs:
- Which of the following are parameters involved in computing the total cost of a software development project ?
- A. Hardware and software costs B. Effort costs C. Travel and training costs D. All of the mentioned...
- What all has to be identified as per risk identification ?
- A. Threats B. Vulnerabilities C. Consequences D. All of the mentioned...
- Which risks are associated with constraints imposed by management or the marketplace ?
- A. Business impact risks B. Process definition risks C. Product size risks D. Development environment risks...
- Which type of software engineering team has a defined leader who coordinates specific tasks and secondary leaders that have responsibility for sub tasks ?
- A. Controlled decentralized (CD) B. Democratic decentralized (DD) C. Controlled centralized (CC) D. None of the mentioned...
- Which of the following process ensures that versions of systems and components are recorded and maintained?
- A. Codeline B. Configuration control C. Version D. Workspace...
Recent Comments