A. an event can’t be accomplished until activities leading to it are completed
B. no activity from any event can be started from preceding event till it is completed
C. length of arrow has nothing to do with time
D. every activity must be completed before end point is reached
E. all of the above
Related Mcqs:
- Expediting function consists in keeping a watch on__________________?
- A. operator’s activity B. flow of material and in case of trouble locate source of trouble C. minimising the delays D. making efficient despatching E. none of the above...
- Father of time study was_________________?
- A. F.W. Taylor B. H.L. Gantt C. F.B. Gilberfh D. R.M. Barnes E. H.B. Maynord...
- Routing is essential in the following type of industry_________________?
- A. assembly industry B. process industry C. job order industry D. mass production industry E. steel industry...
- TMU in method time measurement stands for__________________?
- A. time motion unit B. time measurement unit C. time movement unit D. technique measurement unit E. time method unit...
- Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?
- A. consumes time, but no resources B. consumes resources but no time C. consumes neither time nor resources D. is a dangling event E. consumes both resources and time...
Recent Comments