A. the float may be positive, zero or negative
B. if the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
C. if the float of an activity is negative, delay in its performance is bound to delay the completion of project
D. if the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
E. all of the above
Related Mcqs:
- Which of the following organisations is best suited for steel plants__________________?
- A. functional organisation B. line organisation C. staff organisation D. line, staff and functional organisations E. scalar organisation...
- Current assets include_______________?
- A. manufacturing plant B. manufacturing plant and equipment C. inventories D. common stock held by the firm E. all of the above...
- Father of industrial engineering is_________________?
- A. Jeck Gilberth B. Gnatt C. Taylor D. Newton E. none of the above...
- Choose the wrong statement Time study is used to_________________?
- A. determine overhead expenses B. provide a basis for setting piece prices or incentive wages C. determine standard costs D. determine the capability of an operator to handle the number of machines E. compare alternative methods...
- Emergency rush order can be pushed more effectively in__________________?
- A. job production B. automatic production C. continuous production D. intermittent production E. none of the above...
Recent Comments