Search
.Management Sciences
A. early finish
B. early start
C. late start
D. late finish
E. none of the above
Related Mcqs:
- Inventory control in production, planning and control aims at________________?
- A. achieving optimisation B. ensuring against market fluctuations C. acceptable customer service at low capital investment in inventory D. discounts allowed in bulk purchase E. regulate supply and demand...
- Which one of the following represents a group incentive plan ?
- A. Scanlon Plan B. Rowan Plan C. Bedaux Plan D. Taylor Differential Piece Rate System E. Halsey Premium Plan...
- The main disadvantage of line organisation is_________________?
- A. top level executives have to do excessive work B. structure is rigid C. communication delays occur D. all of the above E. none of the above...
- The allowed time for a job equals standard time plus___________________?
- A. policy allowance B. interference allowance C. process allowance D. learning allowance E. unforeseen allowance...
- Pick up the correct statement from the following?
- A. the float may be positive, zero or negative B. if the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed C. if the float of an activity is negative, delay in its performance is bound to delay the completion of … Pick up the correct statement from the following?Read More...