A. 2
B. 4
C. 8
D. 7
Related Mcqs:
- The normal time required for the completion of project in the above problem is_______________?
- A. 9 days B. 13 days C. 14 days D. 19 days...
- In resources levelling________________?
- A. total duration of project is reduced B. total duration of project is increased C. uniform demand of resources is achieved D. cost of project is controlled...
- A contractor has two options : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he______________?
- A. should invest in neither of the two projects B. could invest in either of the two projects C. should invest in project A D. should invest in project B...
- An excavator costs Rs. 20,00,000/- and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is__________________?
- A. Rs. 8,43,750/- B. Rs. 8,75,000/- C. Rs. 10,50,000/- D. Rs. 11,56,250/-...
- Total float for any activity is defined as the difference between________________?
- A. its latest finish time and earliest start time for its successor activity B. its latest start time and earliest start time C. its latest start time and earliest finish time D. its earliest finish time and earliest start time for its successor activity...