- If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then______________?
- A. expected time of activity A is greater than the expected time of activity B B. expected time of activity B is greater than the expected time of activity A C. expected time of both activities A and B are same D. none of the above...
- A machine is purchased for Rs. 10,000,00/- and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000/-. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is__________________?
- A. Rs. 4,75,000/- B. Rs. 5,75,000/- C. Rs. 6,50,000/- D. Rs. 8,50,000/-...
- In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?
- A. longest duration B. highest cost slope C. least cost slope D. shortest duration...
- Crash project duration is obtained by summing the________________?
- A. normal durations for all the activities B. crash durations for all activities C. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities D. crash durations for all the activities along the critical path obtained by taking into account the crash duration … Crash project duration is obtained by summing the________________?Read More...