Removal of props under______________?

A. slabs spanning upto 4.5 m is 14 days
B. beams spanning upto 6 m is 14 days
C. slabs spanning upto 4.5 m is 7 days
D. All the above

Pick up the correct statement for the web stiffeners?

A. d is the distance between flange angles or the clear distance between flanges
B. vertical stiffeners are spaced at a distance not greater than 1.5 d and not less than 0.33 d
C. for horizontal stiffeners, d is the clear distance between the horizontal stiffener and the tension flange
D. all the above